Wind Farm Clears Final Regulatory Hurdle, Gets Permit
 

Barbara Tetreault
Berlin Daily Sun
June 29, 2010

MILLSFIELD — Granite Reliable Power has cleared the last remaining regulatory hurdle for its proposed 33-turbine wind farm. The U.S. Army Corps of Engineers Friday issued the company a permit to dredge and fi ll 13.5 acres of wetlands.

The federal agency conducted an environmental assessment of the proposed work but decided against requiring a more extensive Environmental Impact Statement. GRP obtained the necessary certifi cate to construct and operate the 99-megawatt wind farm in Dummer and the unincorporated places of Dixville, Millsfield, Odell, and Irvings Location from the New Hampshire Site Evaluation Committee last July. It has been awaiting a decision on the federal permit from the U.S. Army Corps since last fall.

Based on its own environmental assessment, the Army Corps ruled the project would not result in a significant impact - neither beneficial nor detrimental - to the human environment. “As we ready for construction, the issuance of an environmental assessment by the Army Corps of Engineers is another positive step for this wind park,” said GRP Development Director Pip Decker.

The U.S. Army Corps permit contains a number of conditions. It requires GRP to implement the entire mitigation package included in the SEC certificate which stipulates GRP will purchase 1,561 acres of high elevation land as well as 620 acres of forest in the headwaters of Phillips Brook and donate the land to the state. GRP also agreed to provide $200,000 to N.H. Fish and Game for wildlife studies and $750,000 for additional land acquisition.

The Army Corps permit requires GRP to make payment of funds to Fish and Game within six months of the decision and to purchase and transfer the land within nine months. The Army Corps permit stipulates GRP must conduct post construction breeding bird surveys one, three, and five years after the wind farm is completed. The federal agency is requiring a post construction avian and bat mortality study to be submitted no later than 60 days prior to commercialoperation. GRP must also document any anecdotal lynx track sightings.

The Army Corps participated in the SEC public involvement process including the technical sessions, fi nal arguments, and deliberations to allow it to have the full public input in its decision. GRP this spring announced it has hired RMT, Inc., of Madison, Wisconsin to oversee engineering and construction of what will be the largest wind farm in New Hampshire. GRP also reported it has ordered the 33 wind turbines from Vestas of Denmark. Half of the turbines are scheduled to be delivered in the fi rst half of next year and the remainder will arrive in the second half of 2011.

GRP also has contracts to sell 55 percent of the power generated to two Vermont utilities. Central Vermont Public Service Corps will purchase 30 percent of GRP’s output and Green Mountain Power will purchase 25 percent.

Editors Note:  The WMRR club has sent in maps to GRP showing the current location of trails where GRP will interconnect with the grid (at the junction of the old route for PT117 and Corridor 19).  GRP has pledged to work with the club and the NH BOT on relocation of trails if that is necessary.  We are also hoping to reroute some of Corridor 19 away from low lying areas, possibly along the routes of new power lines that are being installed on the west side of Dummer Pond road.  So in addition to being a great project for the area, we think the project will give us an opportunity improve trails in the area of Cor. 19 and PT117.  This is an area that has given us problems for years and we may finally have a way to improve it.

 

 [WMRR Home]